Schedule variance · Whole project
DEMOGC items due · next 14 days
GC items overdue
DEMOScope split · progress and delay by party
ArchicompGCWhole project vs GC scope vs Archicomp scope at the data date, work-weighted from the programme's party hours. Click a column to switch the dashboard scope. DEMO actuals
Archicomp live activity
People working on the Seeb project in ACE360 right now and hours worked today. Counts below 3 are shown as “<3” for privacy.
Programme timeline
Planned dates from the MS Project programme. Bars show planned span; the bright fill is actual progress DEMO. Click a stage to expand.
Progress by discipline · Whole project
Work-weighted planned vs actual % at the data date and schedule variance in days (negative = delay). Discipline codes from the MSP WBS. DEMO actuals
S-curve · cumulative progress
Planned (dashed, from XML) vs actual (solid) DEMO · work-weighted, weekly · whole project, GC and Archicomp scope overlaid
GC deadlines per week
Real planned deadlines of GC obligations; status split DEMO
GC obligations
GC inputs, reviews, acceptances and releases from the programme, rolled up to summary level. Deadlines are real; status DEMO
Deliverables · MDL
Drawings per discipline by responsibility (ACE matrix) – real MDL. ArchicompGC
DD drawings · review status
DD sheets from the MDL; status split DEMO
Planned effort by party
Allocated hours per discipline from the XML (ACE / GC / PENDING / EXT). Archicomp scope = ACE + PENDING, GC scope = GC + EXT. ArchicompGC